Arriva plc / Sovereign Bus & Coach Company Ltd
Administrative Timetable*
*Published on 14 September 2004, as required by Rule 6 of
the Competition Commission Rules of Procedure. Any
further revisions made to the timetable will be published
on this website.
| 3 August 2004 |
Merger reference made |
| August/September/October |
Gather information, issue questionnaires,
hear parties and third parties, site visits |
| Week beginning 27 September |
Publish statement of issues |
| Week beginning 11 October |
First main party hearings |
| October/November |
Verify information, consider provisional
findings |
| Week beginning 1 November |
Second main party hearings |
| 9 November |
Deadline for all parties’ responses/submissions
before provisional findings |
| Week beginning 15 November |
Notify provisional findings |
| Late November |
Consider and notify possible
remedies (if required) |
| Week beginning 6 December |
Remedies hearings(s) (if required) |
| 20 December |
Final deadline for all
parties’ responses/submissions |
| Week beginning 3 January
2005 |
Publish report |
| 17 January 2005 |
Statutory deadline |
|