BAA plc: A report on the economic regulation of the
London airports companies (Heathrow Airport Ltd, Gatwick Airport Ltd and
Stansted Airport Ltd)
Summary of report (html format)
Full text (pdf format)
Adobe Acrobat Reader can be downloaded from http://www.adobe.com
Summary
Under the references made by the Civil Aviation Authority (CAA) on 28
February 2002 (see Appendix 1.1), we are required to recommend the maximum
levels of airport charges at Heathrow Airport Ltd (HAL), Gatwick Airport
Ltd (GAL) and Stansted Airport Ltd (STAL), for the period of five years
beginning on 1 April 2003. (This is the fourth regulatory period since
privatization of the airports, referred to as Q4.) HAL, GAL and STAL are
all subsidiaries of BAA PLC (BAA). We are also required to consider whether
any of the three airport companies have, at any time from the date of
the last references to us in December 1995 up to the date of the current
references, pursued a course of conduct (in relation to matters specified
in the references) which has operated, or might be expected to operate,
against the public interest.
During the current regulatory period (Q3), airport charges per passenger
at Heathrow and Gatwick combined have been required to increase by no
more than RPI-3 and at Stansted by no more than RPI+1. The current reference
follows a substantial review by the CAA of the appropriate basis on which
to set the maximum level of airport charges. In the references to us,
the CAA recommended a formula of RPI+6 at Heathrow, RPI+5 at Gatwick,
and slightly above RPI+6 at Stansted (but did not expect STAL to be able
fully to recover the price cap set). This represented increases in airport
charges per passenger (in 2000/01 prices) between 2002/03 and 2007/08
from £5.37 to £7.25 at Heathrow; from £4.03 to £5.09
at Gatwick; and from £4.47 to £6.10 at Stansted.
During the inquiry, we had to consider a number of general issues relevant
to setting the maximum level of charges, as well as a number of more specific
issues relating to the future costs and revenues of the three airports.
The most controversial aspect of the CAA's recommendations was its proposal
for a 'dual-till' approach. Currently, airport charges are set on a 'single-till'
basis, which takes into account the revenues and costs of BAA's highly
profitable commercial activities (primarily rental income from retail
and other concessionaires). The CAA proposed that they should instead
be set to cover the costs of aeronautical activities, ie those regarded
as essential for the operation of the airport, and monopolizable by the
airport, users therefore having little choice but to use them. This would
exclude not only activities such as retail and catering outlets, but also
surface access to the airports (such as the existing Heathrow Express)
unless required as a condition for planning permission of new facilities
(for example, the extensions to Heathrow Express and Piccadilly lines).
Other things being equal, the dual till would lead to significantly higher
airport charges over the longer term, but in practice the CAA proposed
to set charges for Heathrow in Q4 at a level that was consistent with
a single-till approach, since it regarded that as the reasonable upper
limit for price increases in this period. The CAA proposed that the maximum
level of charges at Gatwick and Stansted in Q4 would, however, be on a
dual-till basis, and that Heathrow should recover in subsequent regulatory
periods the difference between the single-till and dual-till approach
at Heathrow in Q4.
Airlines all objected strongly to the dual-till approach, regarding
it as unnecessarily increasing charges, to the benefit of BAA at the expense
of airlines and, through the higher fares that would result, at the expense
of passengers. Among their other arguments, they regarded commercial activities
as an inseparable part of the aeronautical business; and there were also
concerns that it gave BAA the incentive to favour commercial development
at the expense of aeronautical development.
The main benefits claimed by the CAA and BAA for the dual-till approach
related to effects on investment incentives, efficient utilization of
scarce runway capacity, and deregulation of non-monopoly activities. BAA's
investment programme-about £8 billion from 2002/03 to 2012/13 including
about £3.5 billion on Terminal 5 (T5) at Heathrow-is important to
the airlines. However, we found no evidence that the single till had led
to any general under-investment, nor in current or foreseeable circumstances,
any basis for an expectation that it would do so over the next five years;
nor was it clear that the dual till would lead to better aeronautical
investment in future. The dual till could improve the efficient utilization
of capacity, but the benefits are unlikely to be more than marginal, even
at Heathrow, where there is significant excess demand. The case for the
dual till is, indeed, even weaker in Q4, where the CAA proposed to apply
it only to the less congested airports: GAL and STAL.
Nor do we see significant benefits from any deregulation of BAA's commercial
activities, most of which relates to the leasing of space for retail and
other commercial activities. In so far as airport charges affect fares,
BAA's current relatively high profits from its commercial activities are
mitigated by the fact that they are applied to the benefit of passengers.
The dual-till approach would break this link and may therefore require
increased regulation of such activities. The dual till could also risk
unduly benefiting commercial activities at the expense of aeronautical
activities, which may not attract sufficient funds or management priority.
Against those, at most, limited benefits, we see significant disadvantages
from the dual-till approach. We believe it is difficult sensibly to separate
commercial and aeronautical activities. BAA's rental and other commercial
revenues at the three London airports would not be generated without aeronautical
facilities-commercial and aeronautical facilities are better, therefore,
in our view, and more realistically regarded as one business. Since the
successful development of commercial revenues requires airlines to attract
passengers to the airport, the benefits of commercial activities should
also in our view be shared with airlines and airline users.
The increase in airport charges resulting from the dual till could,
on the basis of some figures we saw, increase the net present value of
revenues to BAA over the longer term by between £3.2 billion and
£3.7 billion. The CAA argued that this would merely be a shift of
economic rents from airlines to the airports, but was unlikely at congested
airports to make a material difference to airfares or passengers: it did
not therefore see such a transfer of rent as of concern to the regulator
in this case. We do not believe average fares would be unaffected at either
congested or uncongested airports. We cannot, however, be indifferent
to such a transfer of resources to a regulated utility whether the effect
was on airlines or their passengers, potentially undermining regulatory
credibility and creating regulatory uncertainty.
It is also difficult, in practice, to allocate either investments or
operating costs between aeronautical and commercial activities. To the
extent that some of the judgements that have to be made are arbitrary,
future disputes about cost allocation could also harm relations between
the airport and its users.
We recognize that the current level of prices particularly at Heathrow
are very substantially below market-clearing prices or the long-run incremental
cost (LRIC) associated with new capacity. But setting market-clearing
prices is not consistent with international obligations, and the net effect
of setting charges equal to LRIC (which would transfer some £10
billion of value from airlines and passengers to BAA) would be very detrimental
to users. Our approach does, however, capture some important elements
of a modified LRIC approach.
One argument put to us for the dual till was that it would raise prices
towards market-clearing or LRIC-based levels. However, in the circumstances
which Heathrow faces for the foreseeable future, the overall balance of
effects on users would remain adverse, and the approach significantly
less acceptable than the one we recommend. We do not therefore share the
view of the CAA that the dual till is best calculated to meet the objectives
of the Airports Act 1986 (Airports Act); in our view, with these objectives
in mind, the single-till approach should be retained for Q4.
Among other aspects of the general approach we had to consider:
(a) In principle we believe that the 'system approach' to setting the
maximum level of airport charges-with respect to the rate of return of
the system as a whole rather than that of each airport-should be retained
under current conditions. However, on the basis of our forecasts this
makes no difference in the period we have to consider due to STAL's increasing
profitability and the current projections of investment requirements of
the airports.
(b) The CAA proposed a price path commitment for future quinquennia. One
element of that commitment would be a significant increase in prices when
T5 came on stream to reflect the high costs of T5, that element of prices
being maintained in future quinquennia. There would also be a commitment
to fix the element of charges relating to the current capital base. Such
a commitment is intended to improve incentives to invest, and reduce the
uncertainty as to the future return on projects which depend on the outcome
of future reviews. In our view, however, there can be no meaningful commitment,
since neither we nor the CAA can prejudge the outcome of future reviews;
we also believe that, even if such a commitment could be given, it may
be undesirable since it would prevent users sharing in the benefits of
future cost reductions. In our view, a preferable, alternative approach
to promoting adequate incentive to invest is to allow for assets in the
course of construction (AICC) subject to a series of triggers relating
charges to progress particularly of T5, but together, where necessary,
with an element of smoothing of return between quinquennia, reducing reliance
on future large increases in charges.
(c) During Q3 there was also allowance for AICC on T5. That investment
could not proceed due to delay in the planning inquiry for T5. There was
also a significant advancement of revenue for such smoothing purposes.
We believe recovery of these revenues and of the effects of under-investment
in Q3 should in principle be allowed for in Q4.
(d) Among more detailed aspects of the formulae, we believe BAA should
still be permitted to pass on 95 per cent of the costs of additional security
requirements given the uncertainty as to the future level of such requirements.
As proposed by the CAA, we recommend that the formulae should apply to
charges as if users pay the full price before discounts; and that revenues
from non-passenger flights should be removed from the cap (subject to
a condition that charges should be no more than for passenger flights).
We have estimated a cost of capital for the three airports of 7.75 per
cent. This reflects in part the extra risk to BAA of the investment in
T5, but which also in our view equally affects the cost of capital of
all three airports. We have also taken into account scope for savings
in operating costs through higher productivity, and lower pension costs.
We have not adjusted BAA's forecasts for capital expenditure: even if
there is scope for lower costs on some projects, there is in our view
likely to be a demand for any cost savings to be spent on additional projects.
We have, however, recommended a number of triggers relating airport charges
to progress particularly on T5.
We have recommended formulae of RPI+6.5 at Heathrow and RPI+0 at Gatwick.
We have based Stansted's cap on its current yield gross of marketing expenditure
of £4.20 at 2000/01 prices throughout Q3, but, for the purposes
of the projections, STAL is assumed to be unable to increase its net charges
to that level within Q4. On this basis, however, each airport earns almost
exactly its cost of capital over the ten years as a whole. The effect
of our recommendation is to result in charges by 2007/08 of £7.82
at HAL and £4.08 at GAL (both in 2000/01 prices). STAL's net charges
are expected to remain below the cap of £4.20. (Our figures are
not directly comparable with the CAA's proposals, however, since they
include the currently separate charge for transfer baggage infrastructure
at Heathrow, and exclude cargo flights at Stansted.)
A wide range of public interest issues were raised with us. Some airlines
were critical about aspects of BAA's investment performance, including
its not promoting additional runway development at Heathrow and delays
to additional pier developments. However, there were in our view good
reasons for BAA's approach, in particular in relation to planning constraints
and uncertainty following the events of 11 September. Underlying the complaints
to us, however, is a perception of inadequate consultation between BAA
and the airlines. The consultation process in Q3 has been hindered by
uncertainty as to the outcome of the T5 inquiry and as to additional runway
developments at one or more of the airports. We nonetheless have significant
reservations about the process of consultation and as those uncertainties
are resolved believe improvements both to consultation and complaints
procedures (which BAA itself proposes to bring about) should be put into
operation.
We also regarded it, however, as unsatisfactory that airlines appear
to have to use five-yearly reviews as the main means to pursue complaints,
many of which should, more properly, in our view, have been addressed
when they arose. We acknowledge the significant constraints on the CAA
resulting from the Airports Act, which hopefully can be resolved when
that Act is brought into line with other legislation. But we also suggest
that the CAA examine whether current procedures under section 41 of the
Airports Act can be made more effective in resolving disputes between
airports and users and whether it has more scope to be involved in relationships
between airlines and users aside from its formal role under that section
of the Airports Act. On one detailed issue, we have found aspects of the
imposition of a levy on taxi drivers at Heathrow to be against the public
interest, and we have put forward an appropriate remedy.
A further main issue related to BAA's quality of service. The CAA had
been concerned with this and believed that BAA's revenue from airport
charges should reflect the quality of service provided. To achieve this
it proposed adding a term in the RPI-X formula which would partly relate
charges to quality of service. We do not believe the average level of
service in Q3 has been poor. We have, however, noted a variability of
quality of service provided; that although service standards were agreed,
they were not comprehensive; that variability in standards has been reflected
in variability of charges in only a few areas; and that users have not
known what quality of service they were entitled to expect. We are in
no doubt that, in a fully competitive market, airport charges would vary
according to the level of service provided, but as regards Heathrow and
Gatwick, during the last quinquennium, this occurred only to a minimal
extent. We find that in failing to conduct themselves so as to make prices
paid sufficiently reflect the levels of service provided, HAL and GAL
have pursued a course of conduct which may be expected to operate against
the public interest. The adverse effect of this conduct is that charges
do not adequately reflect the quality of service provided to the extent
that would occur in a competitive market and in consequence that there
is an absence of the financial incentive to provide the combination of
price and quality of service that would obtain in a competitive market.
We have recommended that HAL and GAL be required to pay specified rebates
to the airlines whenever their quality of service fails to meet such performance
standards as may from time to time be specified by the CAA (guidelines
for which we have set out in our report) together with other requirements
relating to the operation of its Quality of Service Monitor, which we
regard as an important part of monitoring of quality of service.
Full text
Contents
|
Volume 1
|
Summary and Conclusions
|
Part I
|
Summary and Conclusions
|
| Chapter 1 |
Summary |
| Chapter 2 |
Conclusions |
Part II
|
Background and Evidence
|
| Chapter 3 |
Background |
| Chapter 4 |
Financial performance and cost of capital |
| Chapter 5 |
Airport charges and their regulation |
| Chapter 6 |
Quality of service |
| Chapter 7 |
Operating costs and efficiency |
| Chapter 8 |
Commercial and other activities |
| Chapter 9 |
Capital investment |
| Chapter 10 |
Financial projections |
| Chapter 11 |
Views of the CAA and the Department
for Transport |
| Chapter 12 |
Views of airlines and airline representative bodies |
| Chapter 13 |
Views of other third parties |
| Chapter 14 |
Views of BAA |
| |
List of Signatories |
Volume 2
|
Appendices
|
| (The numbering of the appendices indicates
the chapters to which they relate) |
| 1.1 |
The references |
| 2.1 |
Summary of main issues |
| 2.2 |
The effects of increases in airport
charges at congested airports on airline fares |
| 2.3 |
Competition Commission statement on its current thinking
on the single/dual till |
| 2.4 |
Guidelines for the individual elements
of the quality-based rebate scheme |
| 2.5 |
Classification of activities |
| 2.6 |
Heathrow Licensed Taxis Limited |
| 3.1 |
Extracts from ICAO documents and from the Exchange
of Notes on Bermuda 2 |
| 4.1 |
BAA: financial performanceprofit
and loss statements |
| 4.2 |
BAA: financial performancebalance sheets |
| 4.3 |
LAL: financial performance |
| 4.4 |
HAL: financial performance |
| 4.5 |
GAL: financial performance |
| 4.6 |
STAL: financial performance |
| 4.7 |
HAL: financial performance (regulatory
accounting basis) |
| 4.8 |
GAL: financial performance (regulatory accounting basis) |
| 4.9 |
STAL: financial performance (regulatory
accounting basis) |
| 4.10 |
Broad principles of cost allocation in accordance with
the conditions imposed by the CAA under section 40(1)(a)
and (2) of the Airports Act |
| 5.1 |
The CAAs proposed price path
commitment |
| 6.1 |
Details of the CAAs Q-term proposals |
| 6.2 |
Extracts from BAAs paper on service
quality regulation |
| 6.3 |
Views of BA and BAA on measuring and assigning causes
to delays |
| 6.4 |
BA's alternative quality-incentive
proposals |
| 6.5 |
Examples of service level agreements |
| 6.6 |
QSM methodology and detailed scores |
| 6.7 |
BAAs summary of its planning objectives approach |
| 6.8 |
Detailed analysis of IATA survey data |
| 7.1 |
Staff numbers and pay costs |
| 7.2 |
Typical manpower planning processStansted |
| 7.3 |
Roster management system |
| 7.4 |
Employment matters |
| 7.5 |
Pension costs |
| 7.6 |
Absence and labour turnover |
| 7.7 |
Analysis of BAAs productivity targets |
| 8.1 |
Extracts from Donaldsons report |
| 8.2 |
Further information on profits from retail and car park |
| 8.3 |
WDFE: estimated return on capital |
| 8.4 |
Price trends of BAA car parks |
| 9.1 |
BAAs project planning, project
development processes |
| 9.2 |
BAA major projects |
| 9.3 |
BAA major projects by airport |
| 10.1 |
Passenger projections |
| 10.2 |
Regulated capital value at the start
of Q4 |
| 10.3 |
Depreciation and the RCV |
| 12.1 |
Definition of Terminal 5 opening |
| Glossary |
|
| Index |
|
Back to the top
|